Home / Guides / Painting Proposal and Color-Change Order Rules

Painting Proposal and Color-Change Order Rules

Most painting disputes are scope disputes: who prepares what, how many coats, which colors, and what happens when the customer changes their mind after work starts. A written proposal and a simple change order remove most of them.

A proposal that prevents arguments

  • Exact areas: rooms, elevations, cabinets, trim, doors, ceilings.
  • Products by name, sheen and color, with the number of coats.
  • Prep that is included, such as scraping, caulking, patching and priming.
  • Prep that is excluded, such as rot repair, lead-safe work you are not certified for, and furniture moving.
  • Schedule assumptions and weather limits for exterior work.
  • Price, payment schedule, and how long the quote is valid.
  • Customer signature and date.

Compliance note

Painting homes built before 1978 can trigger federal lead-safe rules, and licensing, contract and deposit rules differ by state. Check the EPA's lead-safe guidance and your state contractor board before you use any template, and have your own attorney review final language.

Change orders

A change order is a one-page addendum signed before the extra work begins. It names the change, the added or removed scope, the price effect and any schedule effect. Price a color change like this:

Extra coats       = added coats x area per coat / coverage -> gallons to buy
Extra labor hours = added coat-area / production rate (+ extra prep hours)
Change price      = (extra material + extra labor x crew rate) / (1 - margin)

Example with the interior job above: adding a third finish coat to 3,755 sq ft at 350 sq ft per gallon is 10.73 gallons, bought as 11 gallons at $38 = $418, plus 3,755 / 120 = 31.3 hours at $48 = $1,502. Cost $1,920 divided by 0.70 gives a change price of about $2,742.86.

Rules that keep customers happy

  • Never start extra work on a verbal yes alone; text the change order and wait for the reply.
  • Keep a sample sheen and color approval in writing.
  • Leave a care sheet so the customer does not damage a new finish in the first weeks.