Exterior Prep and Surface Texture Factors for Stucco, Cedar and Masonry
Smooth fiber-cement or vinyl takes paint far more quickly than stucco, rough cedar or block. Rough surfaces absorb more paint, hold more dirt and take longer to roll and back-roll. A surface factor multiplies the paintable area so the gallons and hours reflect that.
Choosing a surface factor
The calculator offers a factor per surface type. The numbers below are illustrative starting points, not industry data: replace them after you compare gallons used and hours worked on completed jobs.
| Surface | Starting factor |
|---|---|
| Smooth siding | 1.00 |
| Cedar or rough-sawn | 1.15 |
| Stucco | 1.25 |
| Masonry or block | 1.35 |
Prep is priced separately
Pressure washing, scraping, sanding, caulking and spot-priming are hours that happen before any topcoat. Estimate them from a walk-around, and write the scope in the proposal so a customer cannot assume it is included.
Worked example (illustrative)
Walls 2,200 sq ft plus 260 sq ft of gables less 300 sq ft of openings, cedar factor 1.15, 380 sq ft of trim, fascia and soffit, 6 hours washing, 14 hours scraping and caulking, $450 lift rental, 300 sq ft per gallon, topcoat $46 and primer $32 per gallon, two topcoats and one primer coat, 90 sq ft per hour, $48 per hour crew rate, 30% margin.
Net area = 2,200 + 260 - 300 = 2,160 sq ft Effective area = 2,160 x 1.15 + 380 = 2,864 sq ft Topcoat gallons= 2,864 x 2 / 300 = 19.09 -> 20 Primer gallons = 2,864 x 1 / 300 = 9.55 -> 10 Paint hours = 2,864 x 3 / 90 = 95.5 Labor hours = 6 + 14 + 95.5 = 115.5 Cost = 1,240 + 5,542.40 + 450 = $7,232.40 Bid = 7,232.40 / (1 - 0.30) = $10,332.00
With a smooth factor of 1.00 the same house bids at $9,348.57; with masonry at 1.35 it bids at $11,496.57. That spread is what the factor protects.